Pilot Study - Budget Report

Name: Issa Fares Date: 2024-19-01 Contact: faresissa22@gmail.com

1. Introduction

This report outlines the budget for the pilot study of a vertical farm project. The project involves the construction of a vertical farming facility from the ground up, incorporating advanced systems for nutrient delivery, environmental control, and lighting. The goal of this pilot study is to validate the feasibility and efficiency of the proposed design.


2. Budget Overview

The budget is divided into the following main sections:

  • I. Building Structure
  • II. Nutrient Delivery System
  • III. Gutter Framework
  • IV. HVAC System
  • V. Specialized Lighting System
  • VI. Overheads
  • VII. Nutrient solution compounds

Each section includes estimated costs, descriptions of components, and justifications for the expense.


3.0 Building Structure

Description

The building structure will be constructed from the ground up, designed to accommodate vertical farming systems. It will include reinforced foundations, walls, and roofing to support the weight of the farming infrastructure and ensure durability.

3.1 Site layout

Figure 1: Site (Top view)

Figure 2: Structural Foundation

Figure 3: Structural columns

Figure 4: Overhead Slab

3.2 Cost Breakdown

Figure 5: Construction Breakdown by Phase (overview)

Table 1: Construction Breakdown by Phase (detailed)
Sub-Structure (₦9,897,800) Super-Structure (₦28,281,000) Blockwork (₦9,188,500) Electrical (₦4,652,500) Finishing (₦10,889,500)
Site Clearing Formwork to Columns and Beams Block to Headcourse Electrical Piping and Wiring Plastering of Walls Both Faces
Excavation of Foundation Casting to Columns and Beams   Fixtures and Fittings Dressing of Doors and Windows
Starter: Columns and Base Formwork to Headcourse     Epoxy Flooring
Casting of Foundation Rebar to Headcourse     Site Clearing to Handover
Blockwork Filled Solid Rebar to Column and Beams      
Casting of Starter Column Casting of Headcourse      
Hardcore Filling and Compaction Formwork to Suspended Roof      
Damp Proof Course (DPC) Rebar to Suspended Roof      
Casting of Suspended Roof      
Table 2: Construction Breakdown by BOM
Description Unit Qty Unit Price (₦) Total (₦)
Reinforcement Y16 for ColumnsUnits6722,7001,520,900
Y16 for BeamsUnits31022,7007,037,000
Y10 for StirmpUnits508,700435,000
Blocks Units12,5227008,765,400
Reinforcements Y12 for Slab Units42012,3005,166,000
Cement BlockworkBags1409,5001,330,000
Casting of ColumnsBags649,500608,000
Casting of SlabBags3509,5003,325,000
Casting of BeamsBags1509,5001,425,000
Casting of DPCBags3609,5003,420,000
Casting of BindingBags1509,5001,425,000
Casting of PlasterBags2009,5001,900,000
External PlasterBags2009,5001,900,000
Marine Boards Units49026,50012,985,000
Bamboo Units3002,300690,000
Braces 2x3Units500200100,000
2x4Units500200100,000
Nails 3 InchBags933,000297,000
6 InchBags635,000210,000
Sand Plaster SandTrips14130,0001,820,000
Sharp SandTrips14140,0001,960,000
Gravel Size 3/4Trips8430,0003,440,000
Laterite Trips1570,0001,050,000
Total 60,909,300
Table 3: Furniture and Utility Items
Location Item Qty Unit Price (₦) Amount (₦)
Office Office Chair 3 65,000 195,000
Office Table 2 120,000 240,000
Cabinet 1 150,000 150,000
Seating Area 1 150,000 150,000
Computer 2 400,000 800,000
Lab Chemical Equipments 1 500,000 500,000
Laboratory Workstation 1 850,000 850,000
Reusable Coverall 10 18,000 180,000
Long Sleeve Latex Gloves 20 2,000 40,000
Disposable Face Masks 400 70 28,000
Steel Seal Doors 4 500,000 2,000,000
Seco-Larm Enforcer Electromagnetic Lock with LED, Bond & Door Position Sensor 2 320,000 640,000
Emergency Glass enclosed Exit Button 3 16,000 48,000
Misc - - 200,000
Total 6,021,000

4.0 Vertical Farm Nutrient Delivery System

Description

The Nutrient Delivery System (NDS) is a critical component of the vertical farm. It includes stainless steel tanks, piping, controllers, sensors, and actuators. The system will be integrated with a SCADA (Supervisory Control and Data Acquisition) system using VTScada for real-time monitoring and control.

4.1 System Overview

The nutrient delivery system is designed to automate the preparation, storage, and distribution of nutrient solutions for a three-level vertical farm. The system ensures precise control of nutrient composition and delivery timing, optimizing plant growth and resource efficiency. It consists of two primary tanks:

  1. Tank A (Mixing Tank): Prepares the nutrient solution by filtering, adjusting electrical conductivity (EC), and pH levels.
  2. Tank B (Reservoir Tank): Stores the prepared solution and delivers it to the vertical farm during scheduled feeding cycles.

The system operates on a 8-minute cycle, divided into two phases:

  1. Mixing Phase (5 minutes): Tank A prepares the nutrient solution by filtering used water, adding fertilizers based on EC readings, and adjusting pH using acid or base solutions.
  2. Pumping Phase (3 minutes): The prepared solution is pumped from Tank A to Tank B at a flow rate of 0.8 L/s.

During this process, Tank B continuously pumps the solution to the vertical farm unit. Each level of the farm receives nutrient solution for 5 minutes, followed by a 10-minute rest period, controlled by solenoid valves to ensure only one level is fed at a time.

4.2 Key Design Considerations

4.2.1 Nutrient Solution Preparation

  • EC Measurement: Fertilizer is added to the solution based on real-time EC readings to maintain optimal nutrient concentration.
  • pH Adjustment: Acid or base solutions are dosed to achieve the desired pH level, ensuring nutrient availability and plant health.
  • Water Source: Used water from the previous cycle is filtered and reused. If insufficient, reverse osmosis (RO) water is added to achieve the required volume.

4.2.2 Cycle Timing and Efficiency

  • The 10-minute cycle (5 minutes mixing + 5 minutes pumping) was determined to be the most appropriate when the mixing time was set to 5 minutes based on flow rate and tank volume calculations, but to give leeway to for correction incase of operational errors, the 8 minute cycle (5 minutes mixing + 3 minutes pumping) was selected.
  • Figure 6 illustrate the relationship between flow rate, tank volume, and cycle timing, confirming the optimal cycle duration.

Figure 6: cycle duration against tanks size requirements (left) and Flow rate (right) when mixing time is set to 3 minutes

  • once the mixing time was set, and the cycle time was found, the tanks sizes A and B wre interpolated and used to draw the tank accordingly. Figure 7 bellow shows the expected cycle for further clarification.

Figure 7: Tank Volumes with respect to time when mixing time is set to 3 minutes

Figure 8: Tank Volumes with respect to time when mixing time is set to 3 minutes with no flow from main supply to Tank A

4.2.3 Tank Sizing and Engineering

  • Using the volumes of Tank A and Tank B that were determined earlier, and with the help of engineering principles guidelines for mixing tanks, the dimensions of the tanks were drawn to scale, shown in Figure 9 below. Examples of the principles used are:
    • The height-to-diameter ratio of 1-1.5 for efficient axial reach.
    • The position, number, and type of blade (in our case, a hydrofoil) for a low-viscosity, non-solid suspended fluid.
    • Lining of the tank with flaps to prevent vortex formation at a protrusion depth of 0.1-0.12 times the diameter of the tank.
    • A bottom dome to prevent stagnation areas.
    • Height redundancy to prevent spillage and a buffer allowance at the flaps to encourage laminar flow at the surface of the solution.

    Figure 9: Tanks A and B final render

  • Tank heights were measured to account for head pressure loss due to elevation, which influences pump selection, pipe selection and system performance that will be reviewed next.

4.2.4 Pipe Sizing and Pressure Loss

To ensure efficient flow rates and minimal energy consumption, a comprehensive analysis was conducted to account for pressure losses arising from pipe length, friction, joints, and elevation changes. These factors were derived from the design layout established during the construction phase. Additionally, the dimensions of the tanks, as designed in earlier stages, and the material properties selected for the system were carefully incorporated into the analysis to guarantee reliable and accurate results.

The flow rate at the pipe network outlet to the gutter system was calculated and fixed as a constant during the fluid mechanics analysis. This resulted in a clear relationship between pipe diameter and pump size. To visualize this relationship, a graph was generated for each pipe, considering only those diameters readily available in the market. This graph served as a critical tool for selecting the most suitable pipe and associated pump ratings, ensuring that the chosen components would operate harmoniously and cost-effectively to achieve the desired performance at the lowest cost possible. Below is the result for each of the pipes/pipe systems.

Refilling Tank A

Figure 10: Diameter against Pump size for the pipe that flows to tank A

  • Length (L): 5 m
  • Flow Rate (Q): 0.00048 m³/s (0.48 L/s)
  • Pipe Diameter (d): 26.6 mm
  • Flow Speed: 0.86 m/s
  • Reynolds Number (Re): 25,222.88 (indicating turbulent flow)
  • Head Loss:
  • Major Head Loss: 0.23 m
  • Minor Head Loss: 0.10 m
  • Elevation: 1.75 m
  • Total Head Loss: 2.08 m
  • Pump Specifications:
  • Efficiency: 80%
  • Power: 13.47 W

Pumping from Tank A to Reservoir (Tank B)

Figure 11: Diameter against Pump size for the pipe connecting tank A to reservoir tank B

  • Length (L): 3.5 m
  • Flow Rate (Q): 0.0008 m³/s (0.8 L/s)
  • Pipe Diameter (d): 26.6 mm
  • Flow Speed: 1.44 m/s
  • Reynolds Number (Re): 42,038.13
  • Head Loss:
    • Major Head Loss: 0.42 m
    • Minor Head Loss: 0.19 m
    • Elevation: 2.20 m
    • Total Head Loss: 2.81 m
  • Pump Specifications:
    • Efficiency: 80%
    • Power: 30.35 W

Reservoir to Gutter Units

  • The pipe network from reservoir Tank B to the gutter units involves multiple connections and pipe diameters.
  • Calculations were performed similarly, but with additional complexity due to the branching network, here the first pipe is called pipe A with subsequent branching following the pattern alphabetically.
  • since the outlet pipes are directly related to required flow rate and the gutter inlet opening, its diameter and solution speed were set as constants respectively.

Figure 12: Diameter against Pump size for the pipe branches A and B from reservoir to gutters

PIPE A PIPE B
Flow Rate (Q): 0.0003 m³/s (8 L/s) Flow Rate (Q): 0.0003 m³/s (8 L/s)
Pipe Diameter (d): 26.6 mm Pipe Diameter (d): 26.6 mm
Flow Speed: 0.54 m/s Flow Speed: 0.54 m/s
Reynolds Number (Re): 15,764.30 Reynolds Number (Re): 15,764.30
Pressure: 34.4-50.6 kPa Pressure: 27.4-43.5 kPa
Head Loss: Head Loss:
- Major: 0.85 m - Major: 0.09 m
- Minor: 0.19 m - Minor: 0.56 m
- Elevation: 3 m - Elevation: 0 m
Total Head Loss at A: 6.65 m Total Head Loss at B: 5.56 m
PIPE C Network A to C
Flow Rate (Q): 0.000012 m³/s (0.32 L/s) Head Loss:
Pipe Diameter (d): 12.7 mm - Major: 0.94 m
Flow Speed: 0.09 m/s - Minor: 0.75 m
Reynolds Number (Re): 1,320.73 (Laminar Flow) - Elevation: 3 m
  Total Head Loss: 4.69 m
Pump Specifications: Pump Efficiency: 80%
Power: 18.96 W  

Precautions

  1. Safety Margins: Elevation values were increased to account for potential variations in pressure loss, ensuring reliable operation.
  2. Material Selection: Using corrosion-resistant materials (stainless steel) for tanks to withstand nutrient solutions.
  3. Automation and Monitoring: Implemented sensors and automation to monitor EC, pH, and flow rates

4.3 Logic control Schema

Figure 13: Simplified overview of the delivery solution system schema

4.4 Cost Breakdown

Table 4: Nutrient Delivery Sensors and Actuators Fixed costs
Component Quantity Unit Price ($) Total ($)
SINAMICS V20 (variable frequency drive) 4 135 540
Siemens S7-1200 PLC 1 1,317 1,317
Expansion SM 1231 AI 8x13 Bit Analog Input 2 250 500
SM 1232 AQ 4x14 Bit Analog Output 2 500 1000
CM 1241 RS485 module (MODBUS COM) 1 240 240
(W)MD-30R(T) ikawi pump 4 384 1,536
Burkert 6281 (Direct-Acting) servo controlled valve 5 25 125
Siemens SITRANS FM MAG DN-25 flow meter 5 300 1,500
VEGAPULS Liquid measuring sensor 2 320 640
Micro controllers 3 120 360
Wiring and components (estimated) 1 300 300
Total 8,058
Table 5: Nutrient Delivery Sensors and Actuators with Tradeoffs
Component Quantity Unit Price ($) Amount ($)
Bluelab Pro Controller Wi-Fi
In stock SKU BCTPRC02
1 1,350 1,350
Bluelab PeriPod M3 1 1,107 1,107
Bluelab pH Probe 5M 1 89 89
Bluelab Pro Controller Conductivity Probe 1 61 61
Acid Tubing (White) Suitable for Bluelab PeriPod 1 80 80
Bluelab Probe Care Kit – pH and Conductivity 1 29 29
Autogrow IntelliClimate Kit 1 1,588 1,588
Total 4,304
or
Four-ring EC/TDS Probe with Internal Temperature Sensor 1 2,300 2,300
EasyFerm Bio pH Sensor 1 1,750 1,750
1413 µS/cm Conductivity Standard in Light Block Bottle (500mL) 1 40 40
Cole-Parmer Masterflex L/S Series 2 1,900 3,800
Watson Marlow 520Di Peristaltic Pump 1 1,400 1,400
SenseAir S8 co2 sensor 1 30 30
Alicat Scientific MC Series flow meter 1 200 200
Dispensing Nozzle 1 40 40
Burkert 6011 valve 1 80 80
Siemens Coriolis Flowmeter SITRANS FC430 Flowmeter 3 300 900
Total 10,540
Table 6: Nutrient Delivery Stainless steel tank construction
Component Quantity Unit Price (₦) Total (₦)
120m 1 inch PVC pipe 50 2,200 110,000
40m 1/2 inch PVC pipe 15 1,800 27,000
Stainless steel 2mm 10 150,000 1,500,000
Hollow Quad Pipe (Stainless 50 X 20 X 2 mm) 4 50,000 200,000
Hollow Circular Pipe (Stainless) 4 25,000 100,000
Labour + fixtures 1 500,000 500,000
Total 2,437,000
  • water from the ground tends to be contaminated with all kind of natural salts, molecules, and elements. To acquire neutral water, the water will pass through a reverse osmosis process with the help of the purification machine shown in figure 14 below. The price varies at about ₦4,000,000.
Figure 14: Reverse Osmosis System
</p>

5.0 Gutter Framework

Figure 15: cycle duration against tanks size requirements (left) and Flow rate (right) when mixing time is set to 5 minutes
</p>

Description

The gutter framework, made of stainless steel, will support the plant beds and ensure proper drainage. It is designed to be durable, easy to clean, capable of reassembly, and resistant to corrosion.

Figure 16: Front view of quartered gutter frame
Figure 17: Side view of quartered gutter frame
Figure 18: Isometric view of gutter frame
Figure 19: Front view of gutter frame
Figure 20: gutter frame final render

5.1 Cost Breakdown

Table 7: Cost breakdown for the construction of the vertical farm Gutters unit
Description Specification Qty Unit Price (₦) Amount (₦)
Hollow Quad Pipe (Stainless) 50 X 50 X 2 mm 12 100,000 1,200,000
Hollow Quad Pipe (Stainless) 50 X 20 X 2 mm 32 50,000 1,600,000
Hollow Circular Pipe (Stainless) D10mm X 2m 24 25,000 600,000
Hollow Circular Pipe (Stainless) D20mm X 2m 6 35,000 210,000
Sheet (Stainless) 2.5 X 2.4 X 1.2 m 24 215,000 5,160,000
Angle Iron (Stainless) 3mm 4 155,000 620,000
Bolt/Nut (Stainless) M40 X 70 1,000 1,200 1,200,000
Roller Tyres (Stainless) R20 4 16,000 64,000
Bearings (Stainless) R20 2 6,000 12,000
Flat Bar (Stainless) 4m X 6m X 3mm 6 120,000 720,000
Total 11,386,000

6.0 HVAC System

Description

The HVAC (Heating, Ventilation, and Air Conditioning) system will regulate temperature, humidity, and air quality within the vertical farm. It is essential for maintaining optimal growing conditions for the plants.

6.1 Cost Breakdown

Table 8: Cost breakdown for the HVAC system (excluding CO2 integration)
Item Model Qty Description Capacity (Kw) Unit Price ($) Total Price ($)
  VRF Outdoor Units  
1 4TVVT192DD07CAA 1 Trane/20HP TVR 7G Modular Cooling Only 56.00 7,011.49 7,011.49
  VRF Indoor Units  
2 4TVBD009AB07RAA 1 Trane TVR 7G Compact Four-way Cassette Unit 2.80 395.78 395.78
3 4TVCD038AB07RAA 1 Trane TVR 7G Four-way Cassette Unit 11.20 704.10 704.10
4 4TVCD055AB07RAA 3 Trane TVR 7G Four-way Cassette Unit 16.00 880.91 2,642.74
  Branch Distributors & Accessories  
5 4TV0RDK01CA007G 1 Trane/IDU Y Joint, kW < 22.4 - 34.69 34.69
6 4TV0RDK03CA007G 3 Trane/IDU Y Joint, 33≤ KW < 104 - 69.96 209.87
Total Price (USD) $10,998.67
Total Price (NGN) ₦17,597,866.00
VAT (7.5%) ₦1,319,839.95
Grand Total ₦18,917,705.95

7.0 Specialized Lighting System

Description

The specialized lighting system will provide the correct spectrum of infrared and visible light to promote optimal plant growth. The lights will be energy-efficient and adjustable to meet the needs of different crops.

7.1 Cost Breakdown

Table 9: LED lights from philips
Component Quantity Unit Price ($) Amount ($)
GreenPower LED production module 42 500 21,000
Ethernet Switch (24-port) 2 100 200
Ethernet Cables 42 7 294
GrowWise Control System (optional) - - -
Total 21,494

8.0 Overheads

Description

The selection of personnel for the vertical farm is based on a balance of technical expertise, agricultural knowledge, and operational efficiency. Engineers specializing in fabrication, control systems, and electrical work ensure the structural integrity, automation, and power management of the farm.

8.1 Cost Breakdown

Table 10: Specialized Employee's projected salaries for the duration of 6 months
Employee Role Monthly Salary (₦) Contract Duration Employment Type Total Salary (₦)
Mechanical Engineer (Fabrication) 300,000 6 months Full-time 1,800,000
Professor in Agriculture (Horticulture) 250,000 4 months Part-time 1,000,000
PhD Student (Agriculture) 180,000 4 months Full-time 720,000
PhD Student (Agriculture) 180,000 4 months Full-time 720,000
Lab Assistant 120,000 4 months Full-time 480,000
Control Systems Engineer 300,000 5 months Full-time 1,500,000
Electrical Engineer 260,000 3 months Full-time 780,000
Total 7,000,000

9.0 Nutrient solution compounds

Description

in the following, we shall break down the required compounds for the production of lettuce and use the data to find a suitable fertilizer

9.1 Nutrient Requirements/ Fertilization

Lettuce requires a well-balanced nutrient solution containing:

  • Nitrogen (N) - for leafy growth
  • Phosphorus (P) - for root development
  • Potassium (K) - for plant vigor and disease resistance
  • Calcium (Ca) - to prevent tip burn
  • Magnesium (Mg) - essential for chlorophyll production
  • Micronutrients such as iron (Fe), zinc (Zn), manganese (Mn), and boron (B)
  • The EC (Electrical Conductivity) of the nutrient solution should be maintained at 1.2 - 2.0 mS/cm, and the pH should be adjusted to 5.5 - 6.5 for optimal nutrient uptake.
Table 11: Macro-nutrient composition and concentrations detected in supplemental water and a nutrient solution with EC of 1.8 mS·cm−1 and pH of 5.8 for hydroponic production of Butterhead lettuce.
Parameter Supplemental water (ppm) Nutrient solution (ppm)
N 0.15 129.18
P 0.31 48.32
K 4.81 183.23
S 8.77 52.10
Ca 37.67 136.52
Mg 10.54 32.68
Based on the Nitrogen (N), Phosphorus (P), and Potassium (K) ratios obtained from the practical data in Table 11, an NPK ratio of **129.18 48.32 183.23** or **2.673 1 3.794** was determined. Given the availability of water-soluble fertilizers suitable for hydroponics, a standard **3 1 4** ratio can be used.

Each head of lettuce requires 5 liters of water throughout its life cycle. In the pilot-scale project, 2,450 heads of lettuce are evenly distributed over 75 m², resulting in a total water usage of 12,250 liters.

Several commercially available fertilizers meet the required NPK ratio, with a maximum cost of $20 per kg, including Sulfur (S), Calcium (Ca), Magnesium (Mg), and various micronutrients.

Note: The fertilizer referenced represents the highest quality and most premium option. For the full-scale project, a custom-blended formulation will be produced in-house by the resident professor of agriculture, at a cost approximately five times lower.

Given the total water requirement, the amount of fertilizer needed is:
12,250 L ÷ 1,000 = 12.25 kg ==> 13kg

9.2 Cost Breakdown

  • The total fertilizer cost at the premium price point would be:

13 Kg × 20 $/Kg = USD 260

  • 2475 lettuce seed are required. the most suitable size available on the market is the 5000 seed bag of premium Salanova Expertise RZ lettuce at USD 280.

  • The cost of 250 Rockwool Plugs is USD 10. 13 packs should suffice with a little extra for contingency, totaling USD 130.


10.Cost & Profit Projections

Description

In the following analysis, the projected profits for both the pilot-scale and main-scale projects will be estimated by considering four key operating costs:

  • Plant seeds and nutrients (with Neutralizers)
  • Electricity
  • Overheads

Since most of these costs have already been estimated, the next step is simply to compile the figures and distribute them across the 75 m² of lettuce production in the pilot-scale setup.

Note: The attached video (also available Here) illustrates the key differences between batch-based lettuce production (pilot scale) and a conveyor belt system (main scale). While batch production is ahead by one complete plant life cycle, this advantage is outweighed by logistical benefits. A continuous daily supply of smaller lettuce increments, rather than a full harvest every 42 days, simplifies sales operations and optimizes storage space. Additionally, using conveyor systems in series allows for dynamic spacing between NFT gutters. Initially, the gutters are placed closely together since young lettuce plants require minimal space. As the conveyor moves forward, the spacing gradually increases, ensuring optimal use of the growing area. In contrast, static batch production requires gutters to be positioned at their maximum spacing from the start, even when the plants are still in the early growth stages. This makes the conveyor system a more space-efficient approach.

10.1 Plant seeds and nutrients

  • The cost of 5000 seed bag of premium Salanova Expertise RZ lettuce is USD 280 , with 33 heads per square meter, the price contribution per m² is USD 1.848.

  • The cost of 250 Rockwool Plugs is USD 10, thus the price per head is $0.04. with 33 heads per m², the contributed cost stands at USD 1.32

  • The cost estimate for of th far end highest quality grade pre-made fertilizer came to $245 for 2,450 Lettuce heads encompassing 75 m², bringing th price per area to USD 3.267.

10.2 Electricity

Total Power Consumption per Hour:

  • Each LED light consumes 88 watts.
  • Total power for 42 lights:

42 lights × 88 watts = 3,696 watts = 3.696 kW

Daily energy consumption:

  • The lights run for 14 hours per day.
  • Daily energy consumption:

3.696 kW × 14 hours = 51.744 kWh/day

Total Energy Consumption Over 42 Days

  • Total energy consumption:

51.744 kWh/day × 42 days = 2,173.248 kWh

Total Electricity Cost:

  • Electricity rate: ₦209.5/kWh.
  • Total cost:

2,173.248 kWh × 209.5 ₦/kWh = ₦ 455,295.46

Price per Area = ₦ 6,070.6

10.3 Overheads

The Employee salary above wont chang much since during the main project since these are specialized personnel while the rest of the staff are mostly Labourers or in the security team. for safety purposes, 100% cost shall still be added on top of the current monthly expenditure of ₦ 1,590,000, bringing the sum of salaries per month to ₦ 3,180,000 or per a complete cycle (48 days) to ₦ 5,088,000.

  • The are used here will be the total area of the main project mentioned above at 25,000 m²

Price per Area (scaled)= ₦ 203.52

10.4 Summary

Table 12: Budget summary overview
Section Sub-Section Cost per m²
USD ($) NGN (₦)
Plant seeds and nutrients Premium Salanova Expertise RZ seeds 1.848 -
Rockwool Plugs 1.32 -
Premium Fertilizer 3.267 -
Electicity Kedco - 6,070.6
Overheads Salaries - 203.52
Total 6.435 6,274.12
  • With the current Exchange rate of 1,500 as of the time of writing,the total NGN cost per m² stands at ₦ 15,926.62, or ₦ 482.62 per Lettuce head.
  • on the other end, during production when we are fully reliant on solar energy, the Electricity bill could very well be nill, and with our own fertilizer mixture at 5x lower in terms of cost, final cost per m² will become ₦ 5,935.62, or ₦ 179.87 per Premium Lettuce head.

10.5 Projections

  • with a base cost of ₦ 179.87 per Lettuce head, adding a redundancy of 25% for Logistics and maintenance, we arrive at a usable cost estimate of ₦224.8 per head.
  • The retail price of local lettuce varies at about ₦500, with retail atr about ₦400. lets assume the company is willing to sell our premium product at the same retail price so we can penetrate the market, profit is about ₦175.2 or 43.8%.
  • The large scales total conveyor system is Exactly 25,000 m² with a daily production of 1,240 NFT gutters and 33 heads per gutter thus the total profit per month is ₦215,075,520 or $143,383.68.

11.0 Summary of Total Costs

Table 12: Budget summary overview
Section Details USD ($) NGN (₦)
Building Structure main structure - 62,909,300
furniture and utility - 6,021,000
Nutrient Delivery System Sensors and Actuators Fixed costs 8,058 -
Sensors and Actuators with Tradeoffs 10,540 -
Stainless steel tank construction - 2,437,000
Reverse Osmosis System - 4,000,000
Gutter Framework vertical farm Gutters unit - 11,386,000
HVAC System 11,824 -
Specialized Lighting 21,494 -
Employees - 7,000,000
Nutrient solution compounds 670 -
Total 52,586 93,753,300
  • With the current Exchange rate of 1,500 as of the time of writing, the Grand Total is thus **$115,088**

12.0 Conclusion

This budget report provides a detailed breakdown of the costs associated with the vertical farm pilot study. The proposed systems and structures are designed to ensure efficiency, durability, and scalability. The next steps involve finalizing the budget, securing funding, and proceeding with the construction and implementation of the pilot study.


results matching ""

    No results matching ""